The Dockets Workflow
Virtual Superintendent captures data from SafeSite and other sources to support electronic docket management.
The general lifecycle of an electronic docket is as follows:
- A subcontractor creates a draft electronic docket in SafeSite and submits it once the work is completed, or a Subcontractor Administrator creates and submits an electronic docket in Virtual Superintendent.
- The docket is assigned to a Supervisor.
- The Supervisor reviews the docket, applies the appropriate cost code, assigns an Engineer, and accepts the docket.
- The Engineer filters their dockets to find those that are Accepted and assigned to them, then reviews and approves the docket.
-
Once approved, the docket is reviewed by a Subcontractor Administrator, who:
- Applies an Invoice Number
- Sets the docket status to Invoiced
- Exports the docket as a detailed spreadsheet
- Sends the spreadsheet and invoice to the Head Contractor Administrator
-
The Head Contractor Administrator filters dockets by Invoice Number and Supplier, then:
- Verifies the submitted invoice against the spreadsheet
- Optionally applies labels to the dockets
- Sets accepted dockets to Reconciled
- Exports reconciled dockets to the head contractor’s financial system for payment
- Archives the dockets once processing is complete